BGJCL
🇳🇵 Official Government-Owned Institution of Nepal
Login
1. Reservoir
Full Supply Level (FSL) El. 540 masl
Maximum Flood Level El. 542 masl
Reservoir Upper Limit with 3m Freeboard El. 545 masl
Minimum Operating Level (MOL) El. 496 masl
Ultimate Minimum Operating Level (MOL.ult.) El. 467 masl
Minimum Reservoir Level (MRL) El. 440 masl
Reservoir Bottom Level El. 326 masl
Total Storage Capacity at FSL 4,467 Mm³
Active Storage between FSL and MOL 2,226 Mm³
Inactive Live Storage between MOL and MOL.ult. 952 Mm³
Conservation Storage between MOL.ult. and MRL 582 Mm³
Dead Storage between MRL and Reservoir Bottom 708 Mm³
Reservoir Surface Area at FSL 63 km²
Reservoir Surface Area at MOL 39 km²
2. Hydrology
Catchment Area 5,005 km²
Long-term Average Discharge 222 m³/s
Construction Period Flood (1 in 20 Years) 3,070 m³/s
Design Flood Discharge (1 in 10,000 Years) 6,260 m³/s
Glacial Lake Outburst Flood (GLOF) 3,000 m³/s
LDOF 5,200 m³/s
Probable Maximum Flood (PMF) 9,800 m³/s
3. Sedimentology
Annual Sediment Inflow 9.8 Million m³/year
Active Storage Loss after 50 Years 7%
Active Storage Loss after 100 Years 13%
4. Diversion System
Design Flood 3,070 m³/s
Tunnel Configuration and Lining Horseshoe-shaped excavation with circular concrete lining
Number of Tunnels 2
Tunnel Diameter 12 m
Length of Diversion Tunnel No. 1 408 m
Length of Diversion Tunnel No. 2 438 m
Upstream Cofferdam Crest Level El. 357 masl
Downstream Cofferdam Crest Level El. 332.50 masl
5. Dam
Dam Type Double-curvature Concrete Arch Dam
Dam Crest Level El. 542 masl + 1.1 m upstream parapet
Maximum Height from Foundation 263 m
Crest Length / Base Width / Crest Width 760 m / 80 m / 8 m
Upstream and Downstream Slopes Variable
Conventional Vibrated Concrete (CVC) 1.92 Million m³
Roller Compacted Concrete (RCC) 3.84 Million m³
Total Concrete Volume 5.75 Million m³
6. Spillway
Type Orifice Gate Spillway with Flip Bucket
Number of Spillway Bays 6
Dimensions of Each Bay Width 5.6 m × Height 8.4 m
Crest Levels 1 at El. 515 masl / 2 at El. 495 masl / 2 at El. 470 masl / 1 at El. 460 masl
Routed Design Flood Discharge 6,280 m³/s for PMF; 4,690 m³/s for Q10000
Gate Type Radial Gates with Hydraulic Hoists
Gate Dimensions 5.6 × 8.4 m, 6 gates
7. Waterway and Powerhouse
Intake Structure Bell-mouth shaped intake structures near the left bank of the dam
Total Design Water Discharge 6 × 112 = 672 m³/s
Number of Intakes 6
Intake Invert Level El. 450 masl; HRT invert level El. 455.60 masl
Stoplog and Wheel Gate Dimensions Span = 4 m / Height = 6 m
Number of Head Race Tunnels (HRT) 6
Intake Tunnel Ø 6 m circular with concrete lining; 107 m horseshoe-shaped excavation section
Head Race Tunnel Ø 5.3 m circular, 22 mm steel lining; lengths from 87 m for Unit 6 to 165 m for Unit 1, horseshoe-shaped excavation section
Pressure Shaft Ø 5.3 m circular, 28–45 mm steel lining, 140 m height
Penstock Ø 5.3 m circular, 45 mm steel lining; lengths from 352 m for Unit 6 to 365 m for Unit 1, horseshoe-shaped excavation section
Powerhouse and Transformer Building Open-type structure on the left bank
Powerhouse Width, Length and Height W 40 m × L 185 m × H 40 m
GIS Building and Potyard Adjacent to the powerhouse on the platform at El. 342
GIS Building Width, Length and Height W 60 m × L 112 m × H 15 m
8. Generating Equipment
Turbine Type Francis Type, Vertical Axis
Number of Turbine Units at Final Stage 6
Net Head at Rated Water Level 200 m
Rated Water Discharge at Final Stage 6 × 112 = 672 m³/s
Installed Generation Capacity 6 × 200 MW = 1,200 MW
Average Annual Energy Generation (Scenario 1) 3,383 GWh
Dry Season Energy (Scenario 1) 1,408 GWh
Wet Season Energy (Scenario 1) 1,975 GWh
Firm Power During Dry Season From 1,200 MW for 8 hours/day in December to 934 MW for 9 hours/day in May
Firm Power During Wet Season From 918 MW for 7 hours/day in June to 928 MW for 4 hours/day in November
Rated Turbine Speed 230.8 rpm
Normal Tailwater Level with 6 Units in Operation El. 323.30 masl
Generator Type Vertical Shaft Rotating Type
Generator Capacity at Final Stage 6 × 235 MVA = 1,410 MVA
9. Transmission Lines
Number of Transmission Lines 2
Voltage 400 kV
Circuit Double Circuit
Conductor Quad Bundle MOOSE
Length from Budhigandaki Hydropower Project to Naubise 40.3 km
Length from Budhigandaki Hydropower Project to Hetauda 58.7 km
10. Substations
Number of Substations 2
Locations One at Naubise and one at Hetauda
11. Costs
Total Capital Cost USD 2,593 Million
Environmental and Social Costs USD 612 Million
Civil Construction Works USD 1,265 Million
Hydropower Equipment and Electrical/Mechanical Equipment (HEM and E&M) USD 571 Million
High Voltage Transmission Lines USD 33 Million
Infrastructure and Roads USD 55 Million
Engineering and Administration USD 57 Million
12. Economic & Financial Parameters
Economic Internal Rate of Return (EIRR) – Same for Low, Medium and High Electricity Demand Projections Generation Scenario 1: 15.5%
Generation Scenario 2: 16.9%
Financial Internal Rate of Return (FIRR) – For Medium Demand Projection Generation Scenario 1: 7.0%
Generation Scenario 2: 8.6%
Average Energy Cost US¢ 6.4/kWh
Payback Period 11 Years / ११ वर्ष
Energy Tariff – 80% Concessional Loan (2% Interest) and 20% Equity Investment Generation Scenario 1: 9 US¢/kWh
Generation Scenario 2: 7 US¢/kWh
100% Public Development Investment with 10% Equity Return Generation Scenario 1: 14.5 US¢/kWh
Generation Scenario 2: 11.5 US¢/kWh
13. Project Benefits
Electricity Sales from Budhigandaki Hydropower Project As mentioned in Section 12
Flood Control in Downstream Areas Reduction in Flood Discharge
Increase in Average Dry Season Flow of the Narayani River at Devghat and Gandak Barrage 50% Increase in Flow from January to May
14. Manpower Requirement
Foreign Manpower 300 / ३०० Persons
Skilled Manpower 570 / ५७० Persons
Semi-skilled Manpower 1,140 / १,१४० Persons
Unskilled Manpower 3,990 / ३,९९० Persons
Total Manpower Requirement 6,000 / ६,००० Persons

Additional Information and River Flow Remarks

Based on river flow measurements conducted during the last five years (2010–2015) at the Budhigandaki River dam site and at the Department of Hydrology and Meteorology's gauging station in Arughat, which has been continuously operating since 1964, the relationship between river flow at Arughat and the dam site has been established more clearly. This is also mentioned in Section 2.1 of the report.

According to the consultant, river flow at the dam site is likely to be approximately 26% higher than estimated in the Feasibility Study Report. While preparing the Feasibility Study Report, a conservative approach was adopted because only limited-period parallel measurement data were available for translating the river flow measured at Arughat to the dam site.

This increase in river flow at the dam site will directly affect the annual energy generation of the Budhigandaki Hydropower Project. According to Generation Scenario 2, annual energy generation is estimated to increase by 26% to approximately 4,250 GWh. Of this, dry-season energy generation is estimated at 1,620 GWh, equivalent to an average of 10.8 GWh per day, with firm power ranging from 970 MW to 1,200 MW.

According to the consultant, five years of parallel river flow measurements between Arughat and the dam site are sufficient to establish reasonable confidence in the revised river flow conversion. However, to fully confirm the project's additional generation potential, continued river flow measurement at the dam site and further data collection have been recommended. This is also mentioned in Sections 4.2 and 4.4 of the Main Report (Ref: BG-DDR-Vol 1 Rev0).

Clean Energy, Prosperous Nepal

Budhigandaki Hydropower Company Limited