| 1. Reservoir | |
| Full Supply Level (FSL) | El. 540 masl |
| Maximum Flood Level | El. 542 masl |
| Reservoir Upper Limit with 3m Freeboard | El. 545 masl |
| Minimum Operating Level (MOL) | El. 496 masl |
| Ultimate Minimum Operating Level (MOL.ult.) | El. 467 masl |
| Minimum Reservoir Level (MRL) | El. 440 masl |
| Reservoir Bottom Level | El. 326 masl |
| Total Storage Capacity at FSL | 4,467 Mm³ |
| Active Storage between FSL and MOL | 2,226 Mm³ |
| Inactive Live Storage between MOL and MOL.ult. | 952 Mm³ |
| Conservation Storage between MOL.ult. and MRL | 582 Mm³ |
| Dead Storage between MRL and Reservoir Bottom | 708 Mm³ |
| Reservoir Surface Area at FSL | 63 km² |
| Reservoir Surface Area at MOL | 39 km² |
| 2. Hydrology | |
| Catchment Area | 5,005 km² |
| Long-term Average Discharge | 222 m³/s |
| Construction Period Flood (1 in 20 Years) | 3,070 m³/s |
| Design Flood Discharge (1 in 10,000 Years) | 6,260 m³/s |
| Glacial Lake Outburst Flood (GLOF) | 3,000 m³/s |
| LDOF | 5,200 m³/s |
| Probable Maximum Flood (PMF) | 9,800 m³/s |
| 3. Sedimentology | |
| Annual Sediment Inflow | 9.8 Million m³/year |
| Active Storage Loss after 50 Years | 7% |
| Active Storage Loss after 100 Years | 13% |
| 4. Diversion System | |
| Design Flood | 3,070 m³/s |
| Tunnel Configuration and Lining | Horseshoe-shaped excavation with circular concrete lining |
| Number of Tunnels | 2 |
| Tunnel Diameter | 12 m |
| Length of Diversion Tunnel No. 1 | 408 m |
| Length of Diversion Tunnel No. 2 | 438 m |
| Upstream Cofferdam Crest Level | El. 357 masl |
| Downstream Cofferdam Crest Level | El. 332.50 masl |
| 5. Dam | |
| Dam Type | Double-curvature Concrete Arch Dam |
| Dam Crest Level | El. 542 masl + 1.1 m upstream parapet |
| Maximum Height from Foundation | 263 m |
| Crest Length / Base Width / Crest Width | 760 m / 80 m / 8 m |
| Upstream and Downstream Slopes | Variable |
| Conventional Vibrated Concrete (CVC) | 1.92 Million m³ |
| Roller Compacted Concrete (RCC) | 3.84 Million m³ |
| Total Concrete Volume | 5.75 Million m³ |
| 6. Spillway | |
| Type | Orifice Gate Spillway with Flip Bucket |
| Number of Spillway Bays | 6 |
| Dimensions of Each Bay | Width 5.6 m × Height 8.4 m |
| Crest Levels | 1 at El. 515 masl / 2 at El. 495 masl / 2 at El. 470 masl / 1 at El. 460 masl |
| Routed Design Flood Discharge | 6,280 m³/s for PMF; 4,690 m³/s for Q10000 |
| Gate Type | Radial Gates with Hydraulic Hoists |
| Gate Dimensions | 5.6 × 8.4 m, 6 gates |
| 7. Waterway and Powerhouse | |
| Intake Structure | Bell-mouth shaped intake structures near the left bank of the dam |
| Total Design Water Discharge | 6 × 112 = 672 m³/s |
| Number of Intakes | 6 |
| Intake Invert Level | El. 450 masl; HRT invert level El. 455.60 masl |
| Stoplog and Wheel Gate Dimensions | Span = 4 m / Height = 6 m |
| Number of Head Race Tunnels (HRT) | 6 |
| Intake Tunnel | Ø 6 m circular with concrete lining; 107 m horseshoe-shaped excavation section |
| Head Race Tunnel | Ø 5.3 m circular, 22 mm steel lining; lengths from 87 m for Unit 6 to 165 m for Unit 1, horseshoe-shaped excavation section |
| Pressure Shaft | Ø 5.3 m circular, 28–45 mm steel lining, 140 m height |
| Penstock | Ø 5.3 m circular, 45 mm steel lining; lengths from 352 m for Unit 6 to 365 m for Unit 1, horseshoe-shaped excavation section |
| Powerhouse and Transformer Building | Open-type structure on the left bank |
| Powerhouse Width, Length and Height | W 40 m × L 185 m × H 40 m |
| GIS Building and Potyard | Adjacent to the powerhouse on the platform at El. 342 |
| GIS Building Width, Length and Height | W 60 m × L 112 m × H 15 m |
| 8. Generating Equipment | |
| Turbine Type | Francis Type, Vertical Axis |
| Number of Turbine Units at Final Stage | 6 |
| Net Head at Rated Water Level | 200 m |
| Rated Water Discharge at Final Stage | 6 × 112 = 672 m³/s |
| Installed Generation Capacity | 6 × 200 MW = 1,200 MW |
| Average Annual Energy Generation (Scenario 1) | 3,383 GWh |
| Dry Season Energy (Scenario 1) | 1,408 GWh |
| Wet Season Energy (Scenario 1) | 1,975 GWh |
| Firm Power During Dry Season | From 1,200 MW for 8 hours/day in December to 934 MW for 9 hours/day in May |
| Firm Power During Wet Season | From 918 MW for 7 hours/day in June to 928 MW for 4 hours/day in November |
| Rated Turbine Speed | 230.8 rpm |
| Normal Tailwater Level with 6 Units in Operation | El. 323.30 masl |
| Generator Type | Vertical Shaft Rotating Type |
| Generator Capacity at Final Stage | 6 × 235 MVA = 1,410 MVA |
| 9. Transmission Lines | |
| Number of Transmission Lines | 2 |
| Voltage | 400 kV |
| Circuit | Double Circuit |
| Conductor | Quad Bundle MOOSE |
| Length from Budhigandaki Hydropower Project to Naubise | 40.3 km |
| Length from Budhigandaki Hydropower Project to Hetauda | 58.7 km |
| 10. Substations | |
| Number of Substations | 2 |
| Locations | One at Naubise and one at Hetauda |
| 11. Costs | |
| Total Capital Cost | USD 2,593 Million |
| Environmental and Social Costs | USD 612 Million |
| Civil Construction Works | USD 1,265 Million |
| Hydropower Equipment and Electrical/Mechanical Equipment (HEM and E&M) | USD 571 Million |
| High Voltage Transmission Lines | USD 33 Million |
| Infrastructure and Roads | USD 55 Million |
| Engineering and Administration | USD 57 Million |
| 12. Economic & Financial Parameters | |
| Economic Internal Rate of Return (EIRR) – Same for Low, Medium and High Electricity Demand Projections | Generation Scenario 1: 15.5%
Generation Scenario 2: 16.9% |
| Financial Internal Rate of Return (FIRR) – For Medium Demand Projection | Generation Scenario 1: 7.0%
Generation Scenario 2: 8.6% |
| Average Energy Cost | US¢ 6.4/kWh |
| Payback Period | 11 Years / ११ वर्ष |
| Energy Tariff – 80% Concessional Loan (2% Interest) and 20% Equity Investment | Generation Scenario 1: 9 US¢/kWh
Generation Scenario 2: 7 US¢/kWh |
| 100% Public Development Investment with 10% Equity Return | Generation Scenario 1: 14.5 US¢/kWh
Generation Scenario 2: 11.5 US¢/kWh |
| 13. Project Benefits | |
| Electricity Sales from Budhigandaki Hydropower Project | As mentioned in Section 12 |
| Flood Control in Downstream Areas | Reduction in Flood Discharge |
| Increase in Average Dry Season Flow of the Narayani River at Devghat and Gandak Barrage | 50% Increase in Flow from January to May |
| 14. Manpower Requirement | |
| Foreign Manpower | 300 / ३०० Persons |
| Skilled Manpower | 570 / ५७० Persons |
| Semi-skilled Manpower | 1,140 / १,१४० Persons |
| Unskilled Manpower | 3,990 / ३,९९० Persons |
| Total Manpower Requirement | 6,000 / ६,००० Persons |
Based on river flow measurements conducted during the last five years (2010–2015) at the Budhigandaki River dam site and at the Department of Hydrology and Meteorology's gauging station in Arughat, which has been continuously operating since 1964, the relationship between river flow at Arughat and the dam site has been established more clearly. This is also mentioned in Section 2.1 of the report.
According to the consultant, river flow at the dam site is likely to be approximately 26% higher than estimated in the Feasibility Study Report. While preparing the Feasibility Study Report, a conservative approach was adopted because only limited-period parallel measurement data were available for translating the river flow measured at Arughat to the dam site.
This increase in river flow at the dam site will directly affect the annual energy generation of the Budhigandaki Hydropower Project. According to Generation Scenario 2, annual energy generation is estimated to increase by 26% to approximately 4,250 GWh. Of this, dry-season energy generation is estimated at 1,620 GWh, equivalent to an average of 10.8 GWh per day, with firm power ranging from 970 MW to 1,200 MW.
According to the consultant, five years of parallel river flow measurements between Arughat and the dam site are sufficient to establish reasonable confidence in the revised river flow conversion. However, to fully confirm the project's additional generation potential, continued river flow measurement at the dam site and further data collection have been recommended. This is also mentioned in Sections 4.2 and 4.4 of the Main Report (Ref: BG-DDR-Vol 1 Rev0).
Clean Energy, Prosperous Nepal
Budhigandaki Hydropower Company Limited